Ive read an article that Site investigation , lets say we are building a Tesco in the future, is notifiable as it is part of the overall project ( to build a tesco). even if it is one bore hole . Ive no issue with that. But cant find the clause to state that fact.
Question - If you are building a big tesco - and you need a connection from a utility before the building starts . That connection will take one day...........is that notifiable? What are your thoughts?
My thoughts is that it is
CDM and pre site work/Site investigation - Question
-
- Posts: 1
- Joined: Fri Jul 16, 2010 10:23 am
- antibot: NO
- Please enter the even number (3628): 3628
-
- Posts: 201
- Joined: Tue Sep 25, 2007 2:15 pm
- Please enter the even number (3628): 9185
- Location: BOLTON
Re: CDM and pre site work/Site investigation - Question
Hi There
There are a number of issues that you raise.
1. Any survey work (bore holes) are not notifiable.
2. All projects over 30 days or 500 man hours are notifiable. This is the project as a whole as opposed to the activities. Notification by the CDM co-ordinator not the subcontractor doing the work.
3. Enabling works, including site establishment, are classed as part of the project.
Hope this helps.
DBP website team.
There are a number of issues that you raise.
1. Any survey work (bore holes) are not notifiable.
2. All projects over 30 days or 500 man hours are notifiable. This is the project as a whole as opposed to the activities. Notification by the CDM co-ordinator not the subcontractor doing the work.
3. Enabling works, including site establishment, are classed as part of the project.
Hope this helps.
DBP website team.
-
- Posts: 1
- Joined: Fri Oct 17, 2014 6:39 am
- antibot: NO
- Please enter the even number (3628): 3628
Re: CDM and pre site work/Site investigation - Question
Ive read an article that Site investigation , lets say we are building a Tesco in the future, is notifiable as it is part of the overall project ( to build a tesco). even if it is one bore hole . Ive no issue with that. But cant find the clause to state that fact.
Are you worried about 300-135 prep and Braindumps certification practice mica Check out our latest resources for www.quincy.edu dumps and
-
- Posts: 201
- Joined: Tue Sep 25, 2007 2:15 pm
- Please enter the even number (3628): 9185
- Location: BOLTON
Re: CDM and pre site work/Site investigation - Question
Check out this link
http://www.hse.gov.uk/construction/cdm/ ... cation.htm
It says under notifications:-
"You should complete an F10 form when you think you are undertaking a project that will last more than 30 days or involve more than 500 person days. This is a legal requirement under the Construction (Design and Management) Regulations 2007. An F10 does not need to be filled in for domestic projects".
http://www.hse.gov.uk/construction/cdm/ ... cation.htm
It says under notifications:-
"You should complete an F10 form when you think you are undertaking a project that will last more than 30 days or involve more than 500 person days. This is a legal requirement under the Construction (Design and Management) Regulations 2007. An F10 does not need to be filled in for domestic projects".