Search found 325 matches

by cross
Mon Mar 31, 2008 8:23 am
Forum: In Review
Topic: 003 - Modular Construction and Installation of Services Rise
Replies: 0
Views: 7542

003 - Modular Construction and Installation of Services Rise

http://www.dbp.org.uk/cs/DBP00003.pdf

Have you used the modular riser technique?

How successful/problematic has it been?

What savings/costs have been gained?
by cross
Mon Mar 31, 2008 8:19 am
Forum: In Review
Topic: 002 - Trimming tops of Concrete Piles
Replies: 0
Views: 7735

002 - Trimming tops of Concrete Piles

http://www.dbp.org.uk/cs/DBP00002.pdf

Do you now use this principle on site.

If so how successful/problematic have you found it to be.
by cross
Mon Mar 31, 2008 8:15 am
Forum: In Review
Topic: 001 - Demolition work within existing buildings
Replies: 0
Views: 8259

001 - Demolition work within existing buildings

http://www.dbp.org.uk/cs/DBP00001.pdf

Has this case study influenced any of your projects.

Have you used or amended the principle shown here.

We would be interested to know of any thoughts on or development of this case study idea.
by cross
Mon Mar 31, 2008 8:10 am
Forum: New
Topic: 125 - Prefabricated Modules
Replies: 0
Views: 8244

125 - Prefabricated Modules

http://www.dbp.org.uk/cs/DBP00125.pdf

Time and effort saved on site.

Thanks to Phil Ramshead of Thermal Transfer Ltd for this submission.
by cross
Mon Mar 31, 2008 8:05 am
Forum: New
Topic: 124 - Support of Heavy Plant
Replies: 0
Views: 8885

124 - Support of Heavy Plant

This has been moved to the learning from bad practice forum.

viewtopic.php?f=5&t=44"
by cross
Mon Mar 31, 2008 8:05 am
Forum: Learning from Bad Practice
Topic: 05 - Support of Heavy Plant
Replies: 1
Views: 21777

05 - Support of Heavy Plant

http://www.dbp.org.uk/cs/DBP00124.pdf

What inherent strength does a wastepaper bin hold?

Is it enough to support a mechanical unit?

Why the principle of using a bin as a support structure may or may not be a good idea.

Thanks to Brian Woodward of Cross Services Eng for this submission.
by cross
Mon Mar 31, 2008 8:02 am
Forum: New
Topic: 123 - 3D Assett Visualisation
Replies: 0
Views: 8286

123 - 3D Assett Visualisation

http://www.dbp.org.uk/cs/DBP00123.pdf

A cost effective way of realising proposed spaces.

Thanks to Andrew Fewster of Boulting Group for this submission.
by cross
Mon Mar 31, 2008 7:57 am
Forum: New
Topic: 122 - Locking off an Isolator Switch
Replies: 0
Views: 8636

122 - Locking off an Isolator Switch

This case study has been moved to the learning from bad practice forum.

viewtopic.php?f=5&t=45&p=53#p53
by cross
Mon Mar 31, 2008 7:57 am
Forum: Learning from Bad Practice
Topic: 04 - Locking off an Isolator Switch
Replies: 0
Views: 19099

04 - Locking off an Isolator Switch

http://www.dbp.org.uk/cs/DBP00122.pdf

Is a cable tie the correct method of locking off an Isolator?

Have a look to find out why it may or may not be.

Thanks to Brian Woodward of Cross Services Eng for this submission.
by cross
Wed Mar 26, 2008 3:53 pm
Forum: Safety
Topic: HSE Shattered Lives Campaign
Replies: 0
Views: 9850

HSE Shattered Lives Campaign

http://www.hse.gov.uk/shatteredlives/

There are some useful posters and information on the above link.

Generally relating to construction and building maintenance.

webmaster@dbp.org.uk
by cross
Fri Mar 07, 2008 3:32 pm
Forum: New
Topic: 121 - Kingspan Koolduct Ducting System
Replies: 0
Views: 8048

121 - Kingspan Koolduct Ducting System

http://www.dbp.org.uk/cs/DBP00121.pdf

Light, quick to install with excellent energy values.

Thanks to Simon Lowry and Jason Riddell of Green Contract Services.
by cross
Fri Mar 07, 2008 3:29 pm
Forum: New
Topic: 120 - Reduced Pressure Zone Valve
Replies: 0
Views: 9606

120 - Reduced Pressure Zone Valve

http://www.dbp.org.uk/cs/DBP00120.pdf


This valve can replace a water tank in certain instances.


Thanks to Craig Soeters of Higgins Plumbing.
by cross
Fri Mar 07, 2008 3:17 pm
Forum: New
Topic: 119 - Commpac Manifold Box
Replies: 0
Views: 7905

119 - Commpac Manifold Box

http://www.dbp.org.uk/cs/DBP00119.pdf

Pipework organised into convenient location for ease of maintenance.
Also helps to minimise disruption.

Thanks to Paul Wilde of Boulting Group for this submission.
by cross
Fri Mar 07, 2008 3:09 pm
Forum: New
Topic: 118 - Dominator Flow ManagementSystem
Replies: 1
Views: 10228

118 - Dominator Flow ManagementSystem

http://www.dbp.org.uk/cs/DBP00118.pdf

Fast installation and easy flushing.

Thanks to Paul Wilde of Boulting Group for this submission.
by cross
Mon Feb 11, 2008 4:25 pm
Forum: New
Topic: 117 - Commisioning Modules Fan Coil and Chilled Beams
Replies: 0
Views: 7977

117 - Commisioning Modules Fan Coil and Chilled Beams

http://www.dbp.org.uk/cs/DBP00117.pdf

Centralized valve locations plus other benefits.


Thanks to John Rush of Boulting Group for this submission.